The Moffett Towers II project is a 1. million-sq.-ft. office development at the former 47.4-acre Lockheed Martin site in Sunnyvale. Development included demolishing 924,500 sq. ft. of existing buildings and constructing five 8-story, 350,633-sq.-ft. office buildings, a 59,211-sq.-ft. amenities structure with swimming pool, an outdoor ampitheater and recreation space, and three parking garages, the first of which will contain 1222 spaces. Total square footage on the property will total approximately 1.8 million sq. ft.

The buildings are steel frame with design-build glass and metal panel curtainwall system and stone. Targeting LEED Platinum.

The project will take place in two phases. Phase I consists of building out the warm shell for Buildings 1 and 2, Parking Structure A (PSA) and the Amenities Building, with associated sitework and demolition.

Related Services

Preconstruction

Design Assist/Design-Build MEP+

Self-Perform Work

Sustainability

LEED® Platinum

EMAIL UPDATES

Signup with your email address below and we will keep you up to date on the latest Level 10 Construction news and project achievements (new , recently completed, awards and recognition)

Thank you for signing up

Project Executive

Casey Wend

Partner/VP Operations
My Ebook (0) + Save- Remove ? Help