The structure is a steel brace frame atop a five-ft.-thick concrete mat slab. Scope included demo of existing parking lot and re-routing of existing utilities away from project excavation.

The project was Design-Build for the MEP systems and shoring. It was critical to get the shoring subconsultant on board early to coordinate with existing site utilities.The building also was constructed on an occupied campus with very tight logistics that included  providing uniterrupted access to the VTA light rail station on the site. Level 10’s team maintained schedule despite having to eliminate unexpected groundwater during construction of the 20-ft.-deep underground parking.

LEED Gold certified.

Related Services

Preconstruction

Design Assist/Design-Build MEP+

Self-Perform Work

Sustainability

LEED® Gold

EMAIL UPDATES

Signup with your email address below and we will keep you up to date on the latest Level 10 Construction news and project achievements (new , recently completed, awards and recognition)

Thank you for signing up

Project Executive

Doug Collins

Partner/Senior VP Operations