Redevelopment of an 18-acre site at the intersection of Central Expressway and Wolfe Road in Sunnyvale into a creative and innovative campus for a leading-edge technology company.
New 882,857 SF design-build campus is comprised of three 6-story connected buildings, each containing two levels of podium parking and four levels of office space; a one-story stand-alone amenities building; and a 7-story free-standing parking structure with 1,540 parking stalls (totaling 518,175 SF). The third floor of each of the three connected buildings will have exterior occupiable spaces at the perimeter of the building, as well as open-to-the-sky courtyards at the core of each sector.
The office buildings and parking garage are post-tensioned concrete structures with nearly 2 million sq. ft. of post-tension deck, including parking structure, parking levels and roofs. Level 10 self-performed the parking structure formwork, foundation concrete and vertical concrete placement.
Sustainability: Surface parking was eliminated through the use of under-building podium parking and a stand-alone garage. Eliminating surface parking allowed for the preservation of 53% of the 18-acre site area as open space. Total of 995 podium parking stalls; 359 on B1 podium totaling 156,446 SF, 321 on B2 podium totaling145,112-sq.-ft., and 315 on B3 podium totaling 144,316 SF.
LEED Platinum.
Related Services
Preconstruction
Design-Build
Design Assist/Design-Build MEP+
Building Information Modeling
Self-Perform Work
Sustainability
Media Gallery (8)
LEED® Platinum
EMAIL UPDATES
Signup with your email address below and we will keep you up to date on the latest Level 10 Construction news and project achievements (new , recently completed, awards and recognition)
Thank you for signing up
Project Executive
Email Casey Wend
Thank you for your message.
We appreciate you taking the time to reach out.
If the nature of your inquiry requires follow up we will reach out to you as soon as possible.
News & Press
-
Awards and Rankings May 12, 2020
Top 10 LEED-Certified Buildings in California
Source: Commercial Property Executive -
In The News November 14, 2018
Level 10 project partner HOK discusses Central + Wolfe “biophilic” design in Wallpaper* magazine
Source: Wallpaper* -
Articles March 16, 2017
Apple’s OTHER new office: Bizarre building shaped like a Mac’s command key revealed near the iPhone maker’s new spaceship HQ
Source: Daily Mail -
Press Releases September 15, 2016
Level 10 Construction Selected as General Contractor for the Central & Wolfe Campus
Source: Level 10 Construction
Awards & Rankings
Top 10 LEED-Certified Buildings in California
Structures at both Moffett Towers II and Central & Wolfe Campus in Sunnyvale are ranked as #2 and #5, respectively.
ACI Construction Awards
Construction Category
Central & Wolfe
ACI Construction Awards
Structural Category
Central & Wolfe
ACI Construction Awards
Architectural Category
Central & Wolfe
American Architecture Award
Central & Wolfe Campus
Largest Projects in SV
Central & Wolfe
#13
13th Largest Construction Project in Silicon Valley
Structures Awards
Deal of the Year
Central & Wolfe
Deal of the Year Winner
Top Starts in CA
Central + Wolfe
#12
12th Largest Construction Start in CA in 2015
Similar Projects
Meta
Meta MPK 21 Menlo Park, CANew 524,000 SF, two-story headquarters with an expansive green roof.
Project Key:
Jay Paul Company
181 Fremont San Francisco, CANew 683,868 SF tower is the safest on the West Coast.
Project Key:
Meta
Meta MPK 20 Menlo Park, CANew 433,555 SF, two-story headquarters with a nine-acre green roof.
Project Key: